Essay
An industrial engineer, who was formerly a real estate developer, wants to estimate the construction costs of an apartment complex that he recently acquired. He gathered the following information: If the total construction cost of the similar property was $2.5 million in the reference year, what is his estimated construction cost in the current year?
Correct Answer:

Verified
Correct Answer:
Verified