Essay
Extreme Wreaths, Inc., makes wreaths in batch sizes of 15 at a time. The cutting and assembly process takes 10 minutes per wreath, and the decorating process time is 7 minutes per wreath. It takes 5 minutes to move the wreaths from the cutting and assembly process to the decorating process.
In an effort to improve the lead time, the company has tried reducing the batch size to 10 units. The new process is as follows: cutting and assembly process-8 minutes. The decorating process is still 7 minutes per wreath. It takes 5 minutes to move the wreaths from the cutting and assembly process to the decorating process.
a. Compute the value-added, non-value-added, and the total lead times of the wreath process for both the old and new manufacturing processes.
b. Compute the value-added ratio for both the old and new processes. Round to one decimal place.
Correct Answer:

Verified
a. Old:
New:
b.Value-Added R...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q63: Kwanika Co. operates in a lean manufacturing
Q64: A quality control activity analysis indicated the
Q65: Peters Manufacturing Co. operates in a lean
Q66: Setup time is disregarded as an improvement
Q67: In a lean accounting system, there are
Q69: In a pull manufacturing system, production is
Q70: Which of the following underlying problems may
Q71: Kilbuck Company operates in a lean manufacturing
Q72: Schedule of Activity Costs <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7934/.jpg" alt="Schedule
Q73: Reducing wait time is not linked to