Multiple Choice
The standard factory overhead rate is $7.50 per machine hour ($6.20 for variable factory overhead and $1.30 for fixed factory overhead) based on 100% of normal capacity of 80,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 15,000 units during August were as follows:
-The fixed factory overhead volume variance is
A) $12,000 unfavorable
B) $12,000 favorable
C) $14,000 unfavorable
D) $26,000 unfavorable
Correct Answer:

Verified
Correct Answer:
Verified
Q122: Use this information for Stringer Company to
Q137: Match each of the following formulas or
Q138: Use this information for Stringer Company to
Q154: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7934/.jpg" alt="
Q155: The standard factory overhead rate is $7.50
Q157: Variances from standard costs are usually not
Q159: Aquatic Corp.'s standard material requirement to produce
Q160: The following data relate to direct materials
Q161: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB7934/.jpg" alt="
Q163: Standard direct materials costs are determined by