Losses in long-term construction projects
A) are generally deferred until the contract is complete.
B) are only recognized immediately under the completed-contract method.
C) are only recognized immediately under the percentage-of-completion method.
D) are recognized immediately under both the completed-contract method and the
Percentage-of-completion method.