Question 29

Multiple Choice

The time to complete a project is inversely proportional to the number of people who are working on the project. A class project can be completed by 3 students in 24 days. In order to finish the project in 6 days, how many more students should the group add?


A) 15 more students
B) 12 more students
C) 18 more students
D) 9 more students