Question 74

Multiple Choice

The systematic follow-up on a capital project to see how the project actually turns out is commonly known as:


A) capital budgeting assessment (CBA) .
B) a postaudit.
C) control of capital expenditures (CCE) .
D) overall cost performance.
E) the cost evaluation phase.