Riverview Manufacturing, Which Produces Electrical Components, Is Contemplating Submitting a Bid
Essay
Riverview Manufacturing, which produces electrical components, is contemplating submitting a bid for 30,000 units of item no. 54. The bid's cost will be follows:
The special device will be purchased for this job and once the job is completed, the device will be discarded.
Riverview applies total manufacturing overhead of $5 to each unit (0.5 machine hours at $10 per hour). This figure is based, in part, on budgeted yearly fixed overhead of $1,440,000 and an anticipated volume of 480,000 machine hours (40,000 per month). Riverview is presently working at 85% of capacity, and the client needs the order in two months.
Required:
A. Is Riverview's current operating environment one of excess capacity or no excess capacity? Briefly explain.
B. If Riverview had excess capacity, what would be the lowest cost total that the company should use when figuring its bid for the order?
C. Can Riverview produce this order in the required time frame of two months? Explain.
D. Suppose that Riverview is in marginal financial health. Explain the benefits and problems of approaching the bidding procedure with (1) a low bid or (2) a high bid.
Correct Answer:

Verified
A. Riverview currently has excess capaci...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q10: Which of the following management tools is
Q11: When introducing new products, some companies use
Q12: Consider the following statements about pricing and
Q13: The following data pertain to Frontier Enterprises:<br><img
Q14: The following questions explore the relationships between
Q16: Use the following information to answer the
Q17: The following costs relate to Tower Company:
Q18: Much of the historical development of the
Q19: If a company has excess capacity, which
Q20: Use the following information to answer the