Bannister Motors Corporation reported the following variances for the period just ended:
Variable-overhead spending variance: $50,000U
Variable-overhead efficiency variance: $28,000U
Fixed-overhead budget variance: $70,000U
Fixed-overhead volume variance: $30,000U
-If Bannister desires to analyze variances that arose primarily from managers' expenditures in excess of anticipated amounts, the company should focus on variances that total:
A) $50,000U.
B) $70,000U.
C) $120,000U.
D) $178,000U.
E) None of the answers is correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: The difference between the total actual factory
Q5: The overhead cost performance report includes spending
Q6: In an activity-based flexible budget, each overhead
Q7: Efficient or inefficient use of a specific
Q8: Use the following information to answer the
Q10: The International Students Club at Eastern University
Q11: With respect to overhead, what is the
Q12: Flexible budgets reflect a company's anticipated costs
Q13: Orlando Company, which applies overhead to production
Q14: Nerve Pain Innovations anticipated that 84,000 process