Multiple Choice
Priority Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended:
Actual units produced: 9,000
Actual variable overhead incurred: $54,400
Actual machine hours worked: 16,000
Standard variable overhead cost per machine hour: $3.50
If Priority estimates two hours to manufacture a completed unit, the company's variable-overhead efficiency variance is:
A) $1,600 favorable.
B) $1,600 unfavorable.
C) $7,000 favorable.
D) $7,000 unfavorable.
E) None of the answers is correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q26: Use the following information to answer the
Q27: The following data pertain to Auxilary Backup
Q28: Use the following information to answer the
Q29: Use the following information to answer the
Q30: Super Fast Insurance uses budgets to forecast
Q32: A static budget:<br>A) is based totally on
Q33: Messenger, Inc. has a standard variable overhead
Q34: Solution Enterprises incurred $828,000 of fixed overhead
Q35: A fixed-overhead volume variance would normally arise
Q36: Tyrant Enterprises, Inc. uses a standard cost