Essay
Waldren Corporation applies fixed manufacturing overhead to production on the basis of machine hours worked. The following data relate to the month just ended:
Actual fixed overhead incurred: $1,245,000
Budgeted fixed overhead: $1,200,000
Anticipated machine hours: 240,000
Standard machine hours per finished unit: 8
Actual finished units completed: 31,250
Required:
A. Compute Waldren's standard fixed-overhead rate per machine hour.
B. Determine Waldren's fixed-overhead budget variance and fixed-overhead volume variance.
C. Calculate the amount of fixed overhead applied to production.
D. Consider the two events that follow and determine whether the event will affect the fixed-overhead budget variance, the fixed-overhead volume variance, both variances, or neither variance. Assume that Waldren has not yet revised its standards to reflect these events if a revision is warranted.
1. A raw material shortage halted production for two days.
2. An additional assembly-line supervisor was hired at the beginning of the month.
Correct Answer:

Verified
A. Budgeted fixed overhead ($1,200,000)/...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q58: Assume that machine hours drive the cost
Q59: Pizzazz Pizza Inc.’s activity based flexible budget
Q60: Barrington Industries anticipated selling 29,000 units of
Q61: The formula flexible budget is more general
Q62: Flexible budgets reflect a company's anticipated costs
Q64: The manufacturing overhead applied to Work-in-Process Inventory
Q65: Use the following information to answer the
Q66: Practical Products plans to manufacture 8,000 units
Q67: The following information relates to Joplin Company
Q68: A flexible budget:<br>A) parallels a static budget