Essay
Halt Company uses a standard cost system and applies manufacturing overhead to products on the basis of machine hours. The following information is available for the year just ended:
Standard variable-overhead rate per machine hour: $2.50
Standard fixed-overhead rate per machine hour: $5.00
Planned activity during the period: 30,000 machine hours
Actual production: 10,700 finished units
Production standard: Three machine hours per unit
Actual variable overhead: $86,200
Actual total overhead: $225,500
Actual machine hours worked: 35,100
Required:
A. Calculate the budgeted fixed overhead for the year.
B. Did Halt spend more or less than anticipated for fixed overhead? How much?
C. Was variable overhead under- or overapplied during the year? By how much?
D. Was Halt efficient in its use of machine hours? Briefly explain.
E. Would the company's efficiency or inefficiency in the use of machine hours have any effect on Halt's overhead variances? If "yes," which one(s)?
Correct Answer:

Verified
A. Let X = budgeted fixed overhead
X* 30...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
X* 30...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q73: In an effort to reduce record-keeping, companies
Q74: A flexible budget for 15,000 hours revealed
Q75: Campaign Company, which applies overhead to production
Q76: The sales-volume variance measures the effect on
Q77: In a standard-costing system, the standard costs
Q79: Use the following information to answer the
Q80: A flexible budget for 15,000 hours revealed
Q81: Use the following information to answer Questions
Q82: The right (credit) side of the production-overhead
Q83: Use the following information to answer the