The Controller for Norton Machining Has Established the Following Overhead

Question 95

Essay

The controller for Norton Machining has established the following overhead cost pools and cost drivers:
The controller for Norton Machining has established the following overhead cost pools and cost drivers:     Order no. 715 has the following production requirements: Machine setups: 7 Raw material: 11,200 units Inspections: 16 Machine hours: 850  Required:  A. Compute the total overhead that should be assigned to order no. 715 by using activity-based costing. B. Suppose that Norton were to use a single, predetermined overhead rate based on machine hours. Compute the rate per hour and the total overhead assigned to order no. 715. C. Discuss the merits of an activity-based costing system in comparison with a traditional costing system.
Order no. 715 has the following production requirements:
Machine setups: 7
Raw material: 11,200 units
Inspections: 16
Machine hours: 850
Required:
A. Compute the total overhead that should be assigned to order no. 715 by using activity-based costing.
B. Suppose that Norton were to use a single, predetermined overhead rate based on machine hours. Compute the rate per hour and the total overhead assigned to order no. 715.
C. Discuss the merits of an activity-based costing system in comparison with a traditional costing system.

Correct Answer:

verifed

Verified

A.
blured image B $538,000/ 20,000 machine hours = ...