Multiple Choice

At a local manufacturing plant, employees must complete new machine set ups within 30 minutes.New machine set-up times can be described by a normal model with a mean of 22
Minutes and a standard deviation of four minutes.What percent of new machine set ups take
More than 30 minutes?


A) 97.72%
B) 47.72%
C) 2.28%
D) 52.28%
E) none of the above