Multiple Choice
Projects S and L are equally risky,mutually exclusive,and have normal cash flows.Project S has an IRR of 15%,while Project L's IRR is 12%.The two projects have the same NPV when the WACC is 7%.Which of the following statements is CORRECT?
A) If the WACC is 10%,both projects will have positive NPVs.
B) If the WACC is 6%,Project S will have the higher NPV.
C) If the WACC is 13%,Project S will have the lower NPV.
D) If the WACC is 10%,both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer:

Verified
Correct Answer:
Verified
Q34: Simms Corp.is considering a project that
Q35: ?Projects A and B have identical expected
Q38: Datta Computer Systems is considering a
Q40: Which of the following statements is CORRECT?<br>A)
Q41: Ehrmann Data Systems is considering a
Q42: Which of the following statements is CORRECT?
Q59: Project S has a pattern of high
Q70: For a project with one initial cash
Q78: If the IRR of normal Project X
Q100: Other things held constant, an increase in