A Company Must Perform a Maintenance Project Consisting of Seven

Question 56

Multiple Choice

A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below: A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below:   Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project) ? A) 9 days B) 10 days C) 11 days D) 12 days E) 13 days Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project) ?


A) 9 days
B) 10 days
C) 11 days
D) 12 days
E) 13 days