Multiple Choice
A company must perform a maintenance project consisting of seven activities.The activities, their predecessors, and their respective time estimates are presented below: Using CPM, which activities have slack in this project?
A) A, B, C
B) B, D
C) Only C
D) C, E
E) F, G
Correct Answer:

Verified
Correct Answer:
Verified