Solved

You Have Collected the Data for a Time-Cost CPM Scheduling

Question 23

Multiple Choice

You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project "direct costs" are given below. You have collected the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the project  direct costs  are given below.   The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ? A) 16 days B) 15 days C) 14 days D) 13 days E) 12 days The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be
$100.At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?


A) 16 days
B) 15 days
C) 14 days
D) 13 days
E) 12 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions