Multiple Choice
PERT charts differ from the critical path method in one important way.What is it?
A) PERT charts assign one time to finish each task; CPM does not.
B) PERT charts are based on the use of quality principles; CPM is not.
C) PERT charts assign three time estimates for each activity; CPM does not.
D) PERT charts can be used in service organizations; CPM cannot.
Correct Answer:

Verified