Multiple Choice
The discounted payback rule may cause: I.some positive net present value projects to be rejected.
II) the most liquid projects to be rejected in favor of less liquid projects.
III) projects to be incorrectly accepted due to ignoring the time value of money.
IV) some projects with negative net present values to be accepted.
A) (I) correct only.
B) (II) correct only.
C) (III) correct only.
D) (IV) correct only.
E) (I) and (IV) correct only.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: The Ziggy Trim and Cut Company can
Q40: All else equal, the payback period for
Q41: The average accounting return is determined by:<br>A)dividing
Q42: The Ziggy Trim and Cut Company can
Q43: Payback is frequently used to analyze independent
Q45: Analysis using the profitability index:<br>A)frequently conflicts with
Q46: Ginny Trueblood is considering an investment which
Q47: If there is a conflict between mutually
Q48: The payback period rule:<br>A)discounts cash flows.<br>B)ignores initial
Q49: The payback period rule accepts all investment