Multiple Choice
A project has an initial cost of £8,500 and produces cash inflows of £2,600, £4,900,and £1,500 over the next three years, respectively.What is the discounted payback period if the required rate of
Return is 7%?
A) 2.13 years.
B) 2.33 years.
C) 2.67 years.
D) 2.91 years.
E) never.
Correct Answer:

Verified
Correct Answer:
Verified