Multiple Choice
Situation 1: Loren Company recently purchased materials from a new supplier at a very attractive price.The materials were found to be of poor quality, and the company's laborers struggled significantly as they shaped the materials into finished product. Situation 2: In a desperate move to make up for some of the time lost, the Loren Company manufacturing supervisor brought in more-senior employees from another part of the plant. Which of the following variances would have a high probability of arising from both of these situations?
A) Situation 1: Material quantity variance, unfavorable; Situation 2: Material price variance, favorable.
B) Situation 1: Material quantity variance, favorable; Situation 2: Material price variance, unfavorable.
C) Situation 1: Material quantity variance, favorable; Situation 2: Labor rate variance favorable.
D) Situation 1: Labor rate variance, favorable; Situation 2: Labor efficiency variance, unfavorable.
E) Situation 1: Labor efficiency variance, favorable; Situation 2: Labor rate variance, favorable.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: The Purchasing Department would normally begin an
Q6: Waterstone Industries is setting standard costs for
Q10: Interactions among variances often occur, making it
Q24: Managerial accountants use either task analysis or
Q46: Which of the following would not be
Q55: Which of the following combinations of direct-material
Q62: Which of the following is a predetermined
Q81: When spending is lower than expected for
Q89: A standard cost:<br>A) is the "true" cost
Q95: Bender Corporation has a favorable materials quantity