Multiple Choice
At Medallion Industries, variable cost per unit is budgeted to be $8.00 and fixed cost per unit is budgeted to be $5.00 in a period when 4,000 units are produced.What is the expected total cost of the units produced at Medallion, if instead, production is actually 5,100 units?
A) $52,000
B) $60,800
C) $66,300
D) $40,800
E) None of these answer choices is correct.
Correct Answer:

Verified
Correct Answer:
Verified