Solved

Berringer Designs Hired a Graphic Artist

Question 9

Multiple Choice

Berringer Designs hired a graphic artist.It is estimated that the artist's learning rate is at 70% and her first quarter's output amounted to 300 relatively equal job outputs, which took her a total of 50 hours to complete.Output is expected to double in every succeeding quarter. What is the total time requirement as of the 5th quarter? (Do not round your intermediate calculations.)


A) 150 hours.
B) 175 hours.
C) 250 hours.
D) 192.08 hours.
E) None of the answers is correct.

Correct Answer:

verifed

Verified

Unlock this answer now