Multiple Choice
You are considering a project which has been assigned a discount rate of 14 percent. If you start the project today, you will incur an initial cost of $1,200 and will receive cash inflows of $600 a year for
Three years. If you wait one year to start the project, the initial cost will rise to $1,250 and the cash
flows will increase to $645 a year for three years. What is the value of the option to wait?
A) $10.16
B) $14.87
C) $19.00
D) $24.08
E) $27.03