Multiple Choice
The fixed costs of a project are $8,000. The depreciation expense is $3,500 and the operating cash flow is $20,000. What is the degree of operating leverage for this project?
A) .40
B) .71
C) .87
D) 1.40
E) 2.50
Correct Answer:

Verified
Correct Answer:
Verified