    The fiXed Costs of a Project Are $8,000
Solved

The fiXed Costs of a Project Are $8,000

Question 187

Question 187

Multiple Choice

The fixed costs of a project are $8,000. The depreciation expense is $3,500 and the operating cash flow is $20,000. What is the degree of operating leverage for this project?


A) .40
B) .71
C) .87
D) 1.40
E) 2.50

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: Fixed costs are variable over long periods

Q182: A project has earnings before interest and

Q183: An increase in variable costs increases the

Q185: Your company's scientists have developed an exciting

Q186: A proposed project has fixed costs of

Q188: When you apply the highest sales price

Q189: Variable costs per unit over a given

Q190: Wilson's Meats has computed their fixed costs

Q191: After ten years as a general auto

Q192: Genevieve has developed a computer software program

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines