Which one of the following costs is most likely a variable cost?
A) Rent paid on an office building.
B) Cost of an equipment lease.
C) Cost of cotton used to produce a shirt.
D) Cost of a computer to process payroll checks.
E) Salary paid to the chief financial officer.
Correct Answer: