A fiNancial Manager Reviewing a Project Is Concerned About the Level

Question 147

Multiple Choice

A financial manager reviewing a project is concerned about the level of forecasting risk in the project's estimated cash flows. The manager should use ___________ to identify the variable that
Presents the highest degree of forecasting risk.


A) Scenario analysis.
B) Simulation analysis.
C) Sensitivity analysis.
D) Break-even analysis.
E) Strategic options analysis.

Correct Answer: