Multiple Choice
Which of the following are advantages of the payback method of project analysis?
A) Considers time value of money, liquidity bias
B) Liquidity bias, arbitrary cutoff point
C) Liquidity bias, ease of use
D) Ignores time value of money, ease of use
E) Ease of use, arbitrary cutoff point
Correct Answer:

Verified
Correct Answer:
Verified