Multiple Choice
Nelson Mfg. owns a manufacturing facility that is currently sitting idle and is debt-free. The facility is located on a piece of land that originally cost $159,000. The facility itself cost $1,390,000 to build. As of now, the book value of the land and the facility are $159,000 and $458,000, respectively. The firm received a bid of $1,700,000 for the land and facility last week. The firm's management rejected this bid even though they were told that it is a reasonable offer in today's market. If the firm was to consider using this land and facility in a new project, what cost, if any, should it include in the project analysis?
A) $0
B) $617,000
C) $1,083,000
D) $1,700,000
E) $1,619,000
Correct Answer:

Verified
Correct Answer:
Verified
Q94: The operating cash flow of a cost-cutting
Q95: Kelly's Corner Bakery purchased a lot in
Q96: GL Plastics spent $1,200 last week repairing
Q97: You own some equipment that you purchased
Q98: The fact that a proposed project is
Q99: Dependable Motors just purchased some MACRS five-year
Q101: The difference between a company's future cash
Q102: The stand-alone principle advocates that project analysis
Q103: A project requires the purchase of $587,000
Q104: Which one of the following would make