Question 13

Multiple Choice

Paolo Brothers Inc. was given the contract to build a school for a local district. Jim Paolo, the project manager of the company, put together a list of activities necessary to complete the project, the time it will take to complete each activity, and each activity's immediate predecessors. This information could be used to construct a(n) _____.


A) SWOT matrix
B) inventory checklist
C) critical path network
D) Six Sigma model