The "Obtaining an Understanding" Work Phase (Phase 1) of Internal

Question 61

Multiple Choice

The "obtaining an understanding" work phase (Phase 1) of internal control evaluation would not give auditors an overall acquaintance with the client's:


A) control environment.
B) information and communication system.
C) control activity effectiveness.
D) monitoring activities.