Multiple Choice
Steel Mill Inc. agrees to deliver a certain quantity of steel to T-Bar Framing Corporation. The agreement states that delivery is to be within "9" days, although the parties intend "90" days. The seller cannot convince the buyer to amend the contract. The most appropriate remedy is most likely
A) a quasi contract.
B) reformation.
C) rescission.
D) specific performance.
Correct Answer:

Verified
Correct Answer: