Multiple Choice
Which of the following is not a criterion that is used to determine whether a project is acceptable under the net present value method?
A) If the net present value is equal to zero
B) If the net present value is greater than zero
C) If the net present value is equal to the required rate of return
D) None of these answers are correct.
Correct Answer:

Verified
Correct Answer:
Verified