Multiple Choice
Continuing to monitor a process to ensure that performance levels are maintained is most closely associated with which element of the DMAIC improvement cycle?
A) Define
B) Control
C) Analyze
D) Improve
Correct Answer:

Verified
Correct Answer:
Verified