Multiple Choice
CPM stands for?
A) Critical posterior method
B) Critical project method
C) Critical path method
D) Critical planning method
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q107: When crashing a project, the project manager
Q108: An activity with a slack time of
Q109: The variance of a project's completion time
Q110: The optimistic activity completion time could occur
Q111: Project management involves all of the following
Q113: Describe the purpose of a Gantt chart
Q114: A contractor indicates that he will be
Q115: A plan to deal with project risks
Q116: Activities with zero slack time are?<br>A) Rarely
Q117: A supplier indicates that he will not