Multiple Choice
A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?
A) A B
B) A B D
C) A C D
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified