Solved

A Project Has Four Activities \rightarrow B
B) A \rightarrow B \rightarrow D
C) A

Question 57

Multiple Choice

A project has four activities. Activity A has no predecessors and a duration of 1 week. Activity B has Activity A as its predecessor and a duration of 4 weeks. Activity C has Activity A as its predecessor and a duration of 3 weeks. Activity D has activities B and C as its predecessors and a duration of 2 weeks. What is the critical path for this project?


A) A \rightarrow B
B) A \rightarrow B \rightarrow D
C) A \rightarrow C \rightarrow D
D) Cannot be determined from the information given

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions