Multiple Choice
Consider a work center with a demand rate of 50 parts per hour and using a container that can hold 12 parts. It is estimated that the container takes 1 hour to cycle through the work cell. Assume a safety stock level of 10 percent. What is the value of K for this system?
A) 2
B) 4
C) 5
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified