Multiple Choice
The last step in DBR production scheduling is to?
A) Identify the constrained resource(s) or bottleneck(s) in the system
B) Synchronize the release of work
C) Use inventory buffers at the critical bottlenecks
D) Forecast the demand
Correct Answer:

Verified
Correct Answer:
Verified