Multiple Choice
If an assembly line has a target takt time of 10 minutes per unit (due to capacity constraints) , how many units per day can be produced? Assume that a production day is 480 minutes.
A) 10 units
B) 48 units
C) 400 units
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer: