Multiple Choice
Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 12, 15, and 10 minutes per unit, respectively. If the assembly line operates for 480 minutes per day with a desired output of 50 units per day, what is the takt time?
A) 0.1 units per minute
B) 13 units per minute
C) 9.6 units per minute
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified