Multiple Choice
Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 12, 15, and 10 minutes per unit, respectively. If the assembly line operates for 480 minutes per day with a desired output of 50 units per day, what is assembly line efficiency?
A) Less than 90%
B) 96%
C) Greater than 98%
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified