Question 76

Multiple Choice

Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 7, 17, and 6 minutes per unit, respectively. What is the sum of task times?


A) 30 minutes per unit
B) 10 minutes per unit
C) 6 minutes per unit
D) Cannot be determined from the information given