Multiple Choice
Assume that an assembly line has three tasks that must be completed (in order, A, B, C, and D) . The tasks have processing times of 8, 12, 9, and 10 minutes per unit, respectively. If the assembly line operates for 500 minutes per day with a desired output of 50 units per day, what is the takt time?
A) 41.7 minutes per unit
B) 10 minutes per unit
C) 62.5 minutes per unit
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified
Q83: Machines that are programmable and able to
Q84: In a material flow map, a triangle
Q85: The bottleneck process governs the processing rate
Q86: There are relatively limited flows within an
Q87: Inventory held downstream of the bottleneck process
Q89: The bottleneck process represents which of the
Q90: In a material flow map, a rectangle
Q91: In a material flow map, a rounded
Q92: A solid line in a material flow
Q93: A focus of material flow in a