Assume that an assembly line has three tasks that must be completed (in order, A, B, C, and D) . The tasks have processing times of 8, 12, 9, and 10 minutes per unit, respectively. If the assembly line operates for 500 minutes per day with a desired output of 50 units per day, what is minimum number of workstations?
A) 4
B) 3
C) 2
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified