Multiple Choice
Two jobs (J1 and J2) are scheduled on two workcenters (WCA and WCB) . J1 starts at time 0 on WCA and finishes on that workcenter at time 5. J2 starts at time 0 on WCB and finishes at time 3. J2 then starts on WCA at time 5 and finishes at time 9. What is the average flow time of these jobs?
A) 0
B) 7
C) 14
D) Cannot be determined from the information given
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Two jobs (J1 and J2) are scheduled
Q10: Having high quality schedules for delivery vehicles
Q11: What type of rules determine which job
Q12: Input and output control refers to?<br>A) Quality
Q13: The average of flow time minus processing
Q15: The ability to produce a wide variety
Q16: Which job shop dispatch rule schedules the
Q17: Which job shop dispatch rule tends to
Q18: Two jobs (J1 and J2) are to
Q19: The orders of some important customers may