Multiple Choice
Which order of processes is correct for ascending order of output volume?
A) Batch Job Shop Assembly Line Continuous
B) Continuous Assembly Line Batch Job Shop
C) Assembly Line Batch Job Shop Continuous
D) Job Shop Batch Assembly Line Continuous
Correct Answer:

Verified
Correct Answer:
Verified