Multiple Choice
A sandwich shop uses a three-person process to build a customer's customized sandwich. One employee takes the customer's order and begins building the sandwich. A second employee then completes the sandwich building. The third employee then wraps the sandwich and takes the customer's payment. The employee that takes the longest time to complete his or her task is referred to as the?
A) Order winner
B) Stop-gap
C) Bottleneck
D) Laggard
Correct Answer:

Verified
Correct Answer:
Verified
Q101: A customer desiring a highly-customized product will
Q102: A process where product is created in
Q103: A doctor's office is considering the purchase
Q104: The maximum number of customers that a
Q105: Effective capacity is expected to be _
Q107: A job shop would be most likely
Q108: A coffee shop is considering the purchase
Q109: A project process is an example of
Q110: Effects of too little capacity include all
Q111: Describe the key differences between make-to-order, make-to-stock,