A process has four stages (A, B, C, and D) . The stages have output rates of 15 units/hr, 10 units/hr, 9 units/hr, and 11 units/hr, respectively. What is the output rate of this process?
A) 15 units/hr
B) 10 units/hr
C) 9 units/hr
D) 11 units/hr