Multiple Choice
An organization may convert from an old system to a new system by choosing to run both the old and new systems at the same time until the new system is fully accepted. This is known as:
A) Cutover
B) Parallel conversion
C) Direct cutover
D) Agile development
E) SDLC
Correct Answer: