Multiple Choice
If someone wants a system cheaply, quickly, and with a large scope, we can conclude:
A) That desire represents the three sides of the Project Triangle
B) This is normally not possible: you can usually only achieve two of those three objectives at a time.
C) Management might be providing an impossible goal.
D) All of the above
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified